  • Under WayOak Park Drainage Improvements

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2026-07-03 ยท Brevard County Public Works (CIP)

    Details

    This project is to assess and improve the drainage where it seems that the wetlands are staging up. Final engineering includes approximately 1400 LF of new storm infrastructure, environmental mitigation, and easement acquisitions.

  • Under Way950 N. Tropical Trail Drainage

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2025-07-01 ยท Brevard County Public Works (CIP)

    Details

    This project includes adding drainage pipes along the east side of N. Tropical Trail right-of-way to the intersection of Lucas Road, and then eastward along the north side of Lucas to a connection with the existing pipe system which carries all runoff for this area to an ultimate outfall ditch north of Lucas Terrace Subdivision and Ormond Ave. The project length is approximately 950 LF along N. Tropical Trail and 350 LF along Lucas Road.

  • PlannedDel Sol Drainage

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2026-03-14 ยท Brevard County Public Works (CIP)

    Details

    Stormwater is currently ponding on the cul-de-sac on the north end of Del Sol Drive. This project aims to improve drainage for the cul-de-sac.

  • Planned330 Hunt Dr Outfall Replacement

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2027-09-16 ยท Brevard County Public Works (CIP)

    Details

    Failing culvert and outfall structure behind the home. Survey outfall area and review for potential design improvements to avoid problem reoccurrence, improve safety, and improve maintenance. Project is located in the rear of 330 Hunt Drive in an apparent drainage easement.

  • PlannedRiverdale Drainage

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2027-05-01 ยท Brevard County Public Works (CIP)

    Details

    Riverdale Drive is a dead end road on the west side of N. Tropical Trail in Merritt Island approximately 1-mile north of W. Merritt Island Causeway. Currently, roadside drainage along Riverdale is limited to natural overland flow from west to east, following natural topographic land features. The natural drainage results in localized ponding in low areas and large overland weirs which result in slow system recovery following rain events. This project aims to capture and convey road run-off and provide positive flow to the apparent outfall in the Roy Keen Ditch in the rear of the properties along the east side of N. Tropical Trail. Easements may be required for potential drainage along lotโ€ฆ

  • PlannedAngel, Teal, & Raven

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2028-12-06 ยท Brevard County Public Works (CIP)

    Details

    This is the continuation of design for drainage and paving for Angel, Teal, and Raven, from the recently completed Newfound Harbor study. Teal and Raven, currently dirt roads, will be paved and brought up to paved road standards with consideration for drainage, and Angel will be retrofitted for drainage improvements with consideration for future drainage infrastructure expansion along Newfound Harbor Drive per the Newfound Harbor study completed by Hanson.

  • PlannedN. Indian River Drive at Brookhill & Briarwood

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2028-10-01 ยท Brevard County Public Works (CIP)

    Details

    Project aims to eliminate stormwater drainage from travel ways, improve overall site drainage, and raise road out of river flood stages via combination of roadside swales, pipes, and raising the road in select locations.

  • PlannedEvans Road at Hibiscus Drainage Improvements

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2025-11-22 ยท Brevard County Public Works (CIP)

    Details

    The project consists of replacing approximately 100 LF of existing double barrel metal pipe with a box culvert at the Evans Road M-1 Canal crossing approximately 150 feet south of Hibiscus Blvd. Also includes sidewalk improvements.

  • PlannedRanch Road Drainage

    Brevard County ยท County project (Drainage) ยท Brevard County Public Works (CIP)

    Details

    Ditch staging along the northside of Ranch Road (FKA Kings Highway) can create backwash effect. It appears to historically drain west into the canal system that outfalls into St. John's. Underdrain that connects this northside ditch and PSJ Unit 7's ditch to the south appears to be a retrofit. Dirt road paving from Grissom to Amesbury. Potential grant funding to pave from Amesbury to nearby school to southwest.

  • PlannedCrane Creek Stabilization

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2030-12-25 ยท Brevard County Public Works (CIP)

    Details

    Nuisance vegetation management uncovered several hardened areas along the creek bank in need of repair. Extent of vegetation removal also necessitated additional stabilization along approximately 925-feet of the creek. This project intends on providing design for replacing the hardened areas of the creek banks and appropriate stabilization measures along the unhardened areas of the creek, permitting, and construction.

  • PlannedNorth Indian River Drive Shoreline & Master Plan

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2025-08-01 ยท Brevard County Public Works (CIP)

    Details

    MASTER PLAN INCLUDES 30% PROJECT CONCEPTS INCLUDES ASSET MAPPING, SURVEYING, ENVIRONMENTAL INVESTIGATION [INCLUDES SHORELINE EXPANSION AND STABILIZATION], DRAINAGE AND UTILITY ANALYSIS, ROADWAY MODIFICATIONS [ELEVATED]. THIS IS A FLOOD PRONE AREA - ROAD IN JEOPARDY OF COLLASPSING DUE TO CLOSE PROXIMITY OF INDIAN RIVER LAGOON (SEVERE EROSION AND SEA LEVEL RISE).

  • PlannedDixie Village Drainage Improvements

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2028-03-14 ยท Brevard County Public Works (CIP)

    Details

    Dixie Village is located west of US Hwy 1 and is generally bound by N Singleton Ave on the west, Parrish Rd to the north, and Westwood Dr to the south. This area has an uncommonly steep natural grade causing stormwater to overcome the existing drainage infrastructure in high intensity rain events. Additionally, a main stormwater pipe between the (platted) Texas Av at the end of Kentucky St and Kirby Drive appears to have failed, causing staging of water during high intensity rain events. The soils in the area are predominantly well drained, sandy soils. This project aims to address the stormwater staging through a combination of upgrading existing drainage infrastructure and addingโ€ฆ

  • PlannedAckerman Ave and Feather St Drainage Improvements

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2025-12-24 ยท Brevard County Public Works (CIP)

    Details

    Blocked Drainage on Ackerman along Swale staging up which causing flooding issue on Ackerman. Low area with pavement swale at the intersection of Feather and Achilles. Water cannot make it along feather to Ackerman to drain south to the outfall and pond at the low areas. The potential future design work consists of elevating flooding issues to resolve local flooding in this area by establishing positive flow to the outfall located east of 7115 Ackerman Ave Cocoa lot based on historical GDC plans. A survey contract has been issued to ETM to survey the area for design purposes of a total of 3,785 LF.

  • PlannedWestwood Drive Drainage

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2027-07-03 ยท Brevard County Public Works (CIP)

    Details

    This projects consists of drainage improvements to reduce the flooding between Bryn Mawr Drive and 3245 Westwood Drive due to heavy rain events. Preliminary concepts include upgrading existing Miami curbing and installing additional curb inlets with the 23-acre contributing watershed.

  • PlannedOakledge Dr Drainage Engineering

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2026-11-21 ยท Brevard County Public Works (CIP)

    Details

    Surveying, engineering and permitting of Oakledge Subdivision for drainage improvements. Drainage outfall easement required.

  • PlannedMaemir Master Drainage Study

    Brevard County ยท County project (Drainage) ยท Brevard County Public Works (CIP)

    Details

    Maemir is a subdivision in unincorporated Brevard County surrounding by improved properties annexed into the City of Rockledge. The residents have reports of periodic flooding of the road and structures within the subdivision, reportedly from a combination of backflow from the Fiske Blvd (FDOT roadway) and blockage of historical flow north and south from the rear lots. Therefore, a multi-jurisdictional effort is being proposed to pursue grant funding to support a master study for the interconnected drainage outfalls surrounding this subdivision to determine if improvements can be made to lower the tailwater in the receiving FDOT outfall ditch to improve drainage for the subdivisionโ€ฆ

  • PlannedIrwin Ave Drainage

    Brevard County ยท County project (Drainage) ยท Brevard County Public Works (CIP)

    Details

    Irwin Avenue has experienced periodic overtopping and delayed recovery following rain events. This study aims to understand the historical considerations for drainage and determine what improvements can be made to improve drainage for the contributing areas.

  • PlannedPalm Avenue Drainage

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2029-02-03 ยท Brevard County Public Works (CIP)

    Details

    Ph1: From the Master Drainage Study in the area, upgrading the culvert underneath International Ave is the first step to fix the backwater effects in the area Ph2: Ditch work, pipe installment, and dirt road base. Preliminary Total Cost Estimate: $3,738,300

  • PlannedInternational Cross Drain

    Brevard County ยท County project (Drainage) ยท Estimated completion: 2028-06-01 ยท Brevard County Public Works (CIP)

    Details

    The cross drain north of Palm Ave is undersized per the recently completed Scottsmoor model and must be upsized to lower upstream staging, particularly for future improvements for Palm Avenue.

Road 10Tap to open
  • Under WayWickham Rd & Pineda Cswy Intersection Improvements

    Brevard County ยท County project (Road) ยท Estimated completion: 2026-05-13 ยท Brevard County Public Works (CIP)

    Details

    A traffic study was completed with recommendations for turn lane improvements at the Wickham Rd & Pineda Cswy intersection in Melbourne.

  • Under WayEllis Road Widening

    Brevard County ยท County project (Road) ยท Estimated completion: 2028-12-31 ยท Brevard County Public Works (CIP)

    Details

    Design, Land Acquisition, Permitting and Construction of a Four Lane Road from John Rodes Boulevard easterly to Wickham Road, including drainage, sidewalks, traffic signals, etc.

  • Under WaySunset Ave Paving Phase 2

    Brevard County ยท County project (Road) ยท Estimated completion: 2025-09-01 ยท Brevard County Public Works (CIP)

    Details

    This project includes paving approximately 1650 LF (0.31 miles) and drainage improvements for the remainder of Sunset Ave to the Old Dixie Way intersection. R/W acquisition needed.

  • Under WayGlenridge & Via de la Reina Connection

    Brevard County ยท County project (Road) ยท Estimated completion: 2026-06-15 ยท Brevard County Public Works (CIP)

    Details

    FDOT to give roughly $150K through an off-system JPA in FY26 for construction of a roadway connection at Glenridge Circle and Via de la Reina. Design and construction in-house.

  • Under WayTemple-Sheridan-Seville Paving

    Brevard County ยท County project (Road) ยท Estimated completion: 2027-09-30 ยท Brevard County Public Works (CIP)

    Details

    Convert dirt roads to paved (asphalt). Approximate lengths: Temple St - 1800 LF (0.34 miles); Sheridan Ave - 2300 LF (0.44 miles); Seville - 5000 LF (0.95 miles).

  • PlannedDixie Way Dirt Road Paving

    Brevard County ยท County project (Road) ยท Estimated completion: 2040-12-01 ยท Brevard County Public Works (CIP)

    Details

    This project includes converting Dixie Way from Grantline Road to County Line Road from a dirt road to an asphalt paved road, approximately 5.4 miles. Land Acquisition is anticipated to be required along the project.

  • PlannedHollywood Blvd Widening

    Brevard County ยท County project (Road) ยท Estimated completion: 2040-10-31 ยท Brevard County Public Works (CIP)

    Details

    This project consists of widening Hollywood Blvd from Palm Bay Road to US192 (approximately 3 miles). Design includes update to Preliminary Engineering Report, 30% and Final Engineering. ROW acquisition is partially funded. Construction is unfunded, but the design is "phased" to facilitate phased construction. ($1.5 set aside const.) Phase 1 - Palm Bay Rd to Eber Blvd. Phase 2 - US192 to Trend Rd. Phase 3 - Trend Rd to Eber Blvd.

  • PlannedS. Courtenay Widening (Cone to Fortenberry)

    Brevard County ยท County project (Road) ยท Estimated completion: 2028-07-17 ยท Brevard County Public Works (CIP)

    Details

    The project involves widening S. Courtenay Pkwy between Cone Rd and Fortenberry Rd from a two lane segment of the roadway to three lanes, with a center bi-directional left turn lane, in order to improve traffic capacity, traffic safety, and functioning of this section of the roadway. 2,600 LF (0.48 miles). Includes landscaping and MIRA coordination.

  • PlannedTangerine St & Vacaro Ave Dirt Road Paving

    Brevard County ยท County project (Road) ยท Estimated completion: 2030-09-30 ยท Brevard County Public Works (CIP)

    Details

    This project is in the Canaveral Groves dirt road paving pilot and would convert Tangerine Street (4200 LF) and Vacaro Avenue (2100 LF) in Cocoa, FL to paved roads. Design may consider 8 inches of millings or double chip seal to serve as a stop gap for future asphalt paving. Refer to design specifications and life cycle analysis from DRMP.

  • PlannedCanaveral Groves Dirt Road Paving (Kumquat, etc.)

    Brevard County ยท County project (Road) ยท Estimated completion: 2032-09-30 ยท Brevard County Public Works (CIP)

    Details

    This project is in the Canaveral Groves dirt road paving pilot and would convert Kumquat Street (2100 LF), Shadwell Avenue (2100 LF), Paddington Street (600 LF), and Navel Street (600 LF) in Cocoa, FL to paved roads. Approximately 5,400 LF total. Design may consider 8 inches of millings or double chip seal to serve as a stop gap for future asphalt paving. Refer to design specifications and life cycle analysis from DRMP.

Sidewalk 8Tap to open
  • Under WayWickham Rd & Aurora Rd Intersection Improvements

    Brevard County ยท County project (Sidewalk) ยท Estimated completion: 2027-02-28 ยท Brevard County Public Works (CIP)

    Details

    This project includes feasibility analysis and design for pedestrian improvements at the intersection.

  • Under WayWickham Rd & Lake Washington Rd Int. Improvements

    Brevard County ยท County project (Sidewalk) ยท Estimated completion: 2026-10-05 ยท Brevard County Public Works (CIP)

    Details

    This project will investigate the feasibility to design pedestrian improvements at the Wickham Rd and Lake Washington Rd intersection in Melbourne. Land acquisition needs are anticipated.

  • Under WayS. Burnett Sidewalk

    Brevard County ยท County project (Sidewalk) ยท Estimated completion: 2025-04-30 ยท Brevard County Public Works (CIP)

    Details

    Addition of approximately 1/4 mile of sidewalk along the west side of S. Burnett Road between Catalina Drive & Parrish Road.

  • Under WayAurora Rd Sidewalk Ph1A (Marywood to Turtlemound)

    Brevard County ยท County project (Sidewalk) ยท Estimated completion: 2023-09-11 ยท Brevard County Public Works (CIP)

    Details

    This project consists of a "re-design" to phase the project of sidewalk on the north side of Aurora Road in Melbourne from west of Marywood Rd to Turtlemound Rd, approximately 3400 LF (0.6 miles).

  • PlannedAurora Rd Sidewalk (Wickham Rd to Croton Rd)

    Brevard County ยท County project (Sidewalk) ยท Estimated completion: 2029-04-01 ยท Brevard County Public Works (CIP)

    Details

    This project consists of widening sidewalk and reconstructing Aurora Rd between Wickham Rd to Croton Rd, approximately 5300 LF (1 mile). Right-of-way impacts anticipated.

  • PlannedBamboo-Akers-Aruin Sidewalk

    Brevard County ยท County project (Sidewalk) ยท Estimated completion: 2027-07-07 ยท Brevard County Public Works (CIP)

    Details

    Requested to investigate the feasibility to construct a sidewalk in Cocoa on Bamboo Ave (Akers Street to Barksdale Street, 3100 LF), Akers St (Bamboo Ave to Homestead Ave, 250 LF), and Ariun St Sidewalk (Bamboo Ave to Homestead Ave, 550 LF) to improve school pedestrian access.

  • PlannedAurora Rd Sidewalk Ph 2 (Turtlemound to Wickham)

    Brevard County ยท County project (Sidewalk) ยท Estimated completion: 2028-04-30 ยท Brevard County Public Works (CIP)

    Details

    This project consists of new sidewalk on the south side of Aurora Rd from Turtlemound Rd to Easy Street (3000 LF) or to Wickham Rd (5200 LF). Survey scope expanded to begin at Turtlemound. Land acquisition needs anticipated.

  • PlannedSheridan SW (Sylvan Dr to Wickham Rd)

    Brevard County ยท County project (Sidewalk) ยท Estimated completion: 2027-10-31 ยท Brevard County Public Works (CIP)

    Details

    This project consists of designing approximately 4650 LF (0.88 miles) of 6โ€™ wide concrete pedway on the south side of Sheridan Road from Sylvan Drive to Wickham Road. The pedway will include connections to the existing sidewalk sections of various subdivisions along Sheridan Road.

Life & Safety 6Tap to open
  • Under WayLib Svs Degroodt Library Roof

    Brevard County ยท County project (F- Life & Safety) ยท Estimated completion: 2026-09-25 ยท Brevard County Public Works (CIP)

    Details

    Replace roof at Degroodt Library

  • Under WayLib Svcs CSR Cent. Library Roof Drain DESIGN ONLY

    Brevard County ยท County project (F- Life & Safety) ยท Estimated completion: 2027-09-30 ยท Brevard County Public Works (CIP)

    Details

    3 areas of roof drain pipes with small leaks at joints previously repaired in approx. 2019. Leaking into 3rd floor storage.

  • PlannedLib Svcs Library Admin Cameras Design Only

    Brevard County ยท County project (F- Life & Safety) ยท Brevard County Public Works (CIP)

    Details

    Replace camera system in 5 libraries. List all 5 libraries.* Adding two more Libraries for design.

  • PlannedFire Rescue_Fire Rescue Supply_ Concrete Sinking

    Brevard County ยท County project (F- Life & Safety) ยท Brevard County Public Works (CIP)

    Details

    The concrete by the back rollup door has sunk more. We are having an issue bringing the fork lift in and out. It needs to get repaired sooner rather than later. There are a few other areas out there that are also beginning to sink. Billy Wahne is aware of issue and is working on it.

  • PlannedLib Svcs CSR Library Roof Drain 1st Floor Leak

    Brevard County ยท County project (F- Life & Safety) ยท Brevard County Public Works (CIP)

    Details

    Roof drain leak on North side of building, located above the catwalk section of the lounge area just inside the library near the garden. lift will be needed

  • PlannedLib Svcs CSR Cent Library Texturize Front Walkway

    Brevard County ยท County project (F- Life & Safety) ยท Brevard County Public Works (CIP)

    Details

    Texturize front walkway-driveway to stairs at front entrance. Area is very slippery during inclement weather. Please check in with director before starting and after job is completed.

Bridge 4Tap to open
  • PlannedN Banana River Drive Bridge - South #704014

    Brevard County ยท County project (Bridge) ยท Estimated completion: 2027-12-06 ยท Brevard County Public Works (CIP)

    Details

    A Feasibility Study is underway to identify design parameters and restrictions related to replacing this bridge and to determine if the geometry of the structure can be optimized for boat clearances. This project is part of a phased replacement of four (4) aging bridges that span separate canals in Merritt Island.

  • PlannedW Central Ave Bridge #704024

    Brevard County ยท County project (Bridge) ยท Estimated completion: 2026-12-01 ยท Brevard County Public Works (CIP)

    Details

    03/13/2025 With the Feasibility Study complete, this bridge site has moved into design. 45%, 90%, 100%, and Bid Plans are the deliverables. Recently, the scope has been expanded to include two (2) relocations of Brevard County's forcemain; the first as a temporary measure, and the second into its final aerial crossing geometry. We expect that BC Utilities will absorb most of the costs (both design and construction) related to the relocations - TBD. Old news: A Feasibility Study is underway to identify design parameters and restrictions related to replacing this bridge and to determine if the geometry of the structure can be optimized for boat clearances. This project is part of a phasedโ€ฆ

  • PlannedN Banana River Drive Bridge - North #704015

    Brevard County ยท County project (Bridge) ยท Estimated completion: 2028-12-04 ยท Brevard County Public Works (CIP)

    Details

    A Feasibility Study is underway to identify design parameters and restrictions related to replacing this bridge and to determine if the geometry of the structure can be optimized for boat clearances. This project is part of a phased replacement of four (4) aging bridges that span separate canals in Merritt Island.

  • PlannedGirard Blvd Bridge #704016

    Brevard County ยท County project (Bridge) ยท Estimated completion: 2029-12-04 ยท Brevard County Public Works (CIP)

    Details

    A Feasibility Study is underway to identify design parameters and restrictions related to replacing this bridge and to determine if the geometry of the structure can be optimized for boat clearances. This project is part of a phased replacement of four (4) aging bridges that span separate canals in Merritt Island.

Traffic 4Tap to open
  • PlannedGrissom Pkwy & Canaveral Groves Intx Improvements

    Brevard County ยท County project (Traffic) ยท Brevard County Public Works (CIP)

    Details

    Brevard County has requested Kimley-Horn and Associates, Inc. to perform an Intersection Safety Study for the intersection of Grissom Pkwy & Canaveral Groves Blvd. This study includes examining of existing conditions and proposing modifications to the intersection configuration, as well as designing the conversion of the existing span wire to a mast arm system.

  • PlannedWickham Rd and Post Rd Intersection Improvements

    Brevard County ยท County project (Traffic) ยท Brevard County Public Works (CIP)

    Details

    The purpose of this project is to add a southbound right turn lane to improve overall safety and operation of the intersection as well as the level of service for Wickham Road, as identified in the Feasibility Study for this intersection improvement. The volume of southbound right turn traffic reduces the rate at which southbound through traffic can move effectively through the intersection. Separating the right turn queue by provide a dedicated right turn lane will improve signal operation, reduce intersection delay, and improve traffic progression on Wickham Road. Design performed by Metric Engineering, Inc., with project management by AtkinsRealis.

  • PlannedWickham Rd & Business Center Structural/Concept

    Brevard County ยท County project (Traffic) ยท Brevard County Public Works (CIP)

    Details

    Brevard County has requested Kimley-Horn and Associates, Inc. to analyze the loading on the span wire system at Wickham Rd & Business Center Blvd to determine if additional signal heads EB/WB can be added. Associated with this are a concept of the required strain pole modification (short-term) and concept of conversion to a mast arm system (longer-term).

  • PlannedStadium Parkway at Cuddington Drive Signalization

    Brevard County ยท County project (Traffic) ยท Estimated completion: 2025-05-30 ยท Brevard County Public Works (CIP)

    Details

    Signalization of the intersection including roadway modifications to include extending the left turn lane heading southbound to 375 ft, extending the left turn lane heading northbound to 510 ft, and update existing median islands.

Other 3Tap to open
  • Under WayBrevard families invited to honor loved ones lost in traffic crashes

    Brevard County ยท News headline ยท Hometown News Brevard (via Google News)

  • Under WayParks & Rec Port St John CC HVAC

    Brevard County ยท County project (F- Mechanical) ยท Estimated completion: 2027-03-28 ยท Brevard County Public Works (CIP)

    Details

    HVAC unit 5 is shut down and out of refrigerant.

  • PlannedSea Ray Bridge Replacement

    Brevard County ยท County project (Transportation) ยท Estimated completion: 2026-02-06 ยท Brevard County Public Works (CIP)

    Details

    The storm-damaged bridge (due to excessive scour) is to be replaced. Plans are to be developed through 'For Construction' plans, with Design Consultant to provide post-award services. Construction Engineering Inspection (CEI) services will also be required - CEI team TBD.